Incident dateReport
publication date
ReportResponse to
RAIB
26/03/202009/11/2020Signal passed at danger at Loughborough South JunctionORR response dated 3 November 2021
23/03/202019/11/2020Passenger train collision with a derailed locomotive at Bromsgrove

ORR response dated 3 February 2022

ORR response dated 6 October 2021

09/03/202023/12/2020Runaway and derailment of a wagon at Clitheroe, LancashireORR response dated 22 January 2022
25/01/202028/09/2020Collision between mobile elevating work platforms at Rochford, Essex

ORR response dated 28 October 2022

ORR response dated 21 September 2021

23/01/202016/11/2020Derailment of a freight train near Wanstead Park, London

ORR response dated 28 November 2022

ORR response dated 28 October 2022

24/11/201914/12/2020Near miss at Norwich Road level crossing, Norfolk

ORR response dated 6 December 2021

ORR response dated 1 August 2024

01/08/201928/05/2020Loss of brake control on a sleeper train approaching Edinburgh

ORR response dated 6 August 2021

ORR response dated 1 February 2021

03/07/201912/11/2020Track workers struck by a train at Margam

ORR response dated 28 March 2024

ORR response dated 7 February 2024

ORR response dated 8 August 2023

ORR response dated 03 February 2023

ORR response dated 28 October 2022

ORR response dated 10 November 2021

13/06/201926/05/2020Train collision with material washed out from a cutting slope at Corby, Northamptonshire

ORR response dated 3 February 2023

ORR response dated 24 May 2021

17/05/201903/08/2020Signal passed at stop and near miss, Deansgate-Castlefield

ORR response dated 6 October 2021

ORR response dated 2 August 2021

06/05/201925/08/2020Freight train derailment at Willesden High Level Junction, north-west London

ORR response dated 31 March 2022

ORR response dated 24 August 2021

20/04/201903/02/2020Serious operational irregularity at Balham on 20 April 2019

ORR response dated 7 February 2024

ORR response dated 28 October 2022

ORR response dated 4 December 2020

16/04/201906/02/2020Runaway locomotive at Beddgelert, North Wales on 16 April 2019

ORR response dated 6 August 2021

ORR response dated 5 February 2021

N/A12/05/2020Class investigation into factors affecting safety-critical human performance in signalling operations on the national networkORR response dated 8 August 2022