Our responses to the Rail Accident Investigation Branch (RAIB) in relation to their recommendations published in 2015.

Incident date Report publication date Report Response date Response to RAIB
07/03/2015 07/12/2015 Container detachments, Cumbria and Lincolnshire   Not applicable as no
recommenadtions in the report
29/01/2015 21/10/2015 Arcing and fire at Windsor & Eton Riverside 20/10/2016

ORR response to RAIB

ORR response on 04/12/20

28/01/2015 07/10/2015 Platform struck by trains at Moston 06/10/2016

ORR response to RAIB

ORR response to RAIB on 21/08/18

ORR response on 16/03/21

28/12/2014 16/12/2015 Unsafe events at Heathrow Tunnel Junction 04/08/2016

ORR response to RAIB

ORR response to RAIB on 14/02/17

ORR response to RAIB on 11/12/17

ORR response on 27 May 2021

ORR response on 06/08/21

ORR response on 04/08/23

17/11/2014 23/09/2015 Collision with a collapsed signal post at Newbury 21/09/2016

ORR response to RAIB

ORR response on 03/02/23

01/11/2014 17/08/2015 Near miss at Raven level crossing 16/08/2016

ORR response to RAIB

ORR response to RAIB on 14/02/17

26/10/2014 14/08/2015 Train struck and damaged in Watford Tunnel 03/08/2016

ORR response to RAIB

ORR response on 20/04/17

ORR response to RAIB on 11/10/22

23/10/2014 24/09/2015 Derailment at Heworth 04/08/2016

ORR response to RAIB

ORR Response on 26/04/17

ORR response to RAIB on 07/06/19

ORR response on 12/06/20

02/10/2014 06/08/2015 Derailment at Porthkerry 05/08/2016

ORR response to RAIB

ORR response to RAIB on 30/08/17

23/09/2014 24/06/2015 Train driver receiving a severe electric shock at Sutton Weaver, Cheshire 21/04-2016

ORR response to RAIB

ORR response to RAIB on 06/10/17

ORR response to RAIB on 03/04/19

22/09/2014 16/07/2015 Near miss involving track workers near Hest Bank, Lancashire 07/04/2016

ORR response to RAIB on 07/04/2016

ORR response to RAIB on 11/01/17

ORR response to RAIB on 16/06/17

11/08/2014 30/07/2015

Parting of live overhead wire at Walkergate

03/12/2015

ORR response to RAIB

ORR response on 13/02/20

24/06/2014 15/06/2015 Accident to a track worker near Redhill 07/04/2016

ORR response to RAIB on 07/04/2016

ORR response to RAIB on 11/01/17

ORR response to RAIB on 11/12/17

ORR response on 1 April 2021

25/05/2014 30/04/2015 Derailment of an empty passenger train at Paddington station 21/04/2016

ORR response to RAIB on 21/04/16

ORR response to RAIB on 06/09/17

11/05/2014 28/05/2015 Fatal accident at Frampton level crossing 13/05/2016

Letter to RAIB on 16/07/15 regarding published report

ORR response on 13/05/16

ORR response on 26/04/17

ORR response on 07/12/20

ORR response on 14/03/22

14/05/2014 21/05/2015 Runaway and subsequent collision near to
Loughborough Central station, Great Central
Railway
09/05/16 ORR response to RAIB
02/04/2014 12/08/2015

Derailment of freight train at Angerstein Junction

06/07/2016

ORR response to RAIB

ORR response to RAIB on 08/02/19

ORR response to RAIB on 10/06/19

ORR response to RAIB on 03/12/19

22/01/2014 16/02/2014 Fatal accident involving a track worker near Newark North Gate station 09/02/2016

ORR response 09/02/2016

ORR response 11/04/2018

27/08/2013 02/04/2015 Derailment of a freight train at Stoke Lane Level Crossing 03/03/2016

ORR response to RAIB on 03/03/16

ORR response on 8 October 2018

ORR response on 13/08/19

ORR response on 23/08/22

N/A 20/08/2015 Class investigation – protection irregularities 06/07/2016

ORR response to RAIB

ORR response on 20/02/18